With the help of the family we started with the prep for the electrics before the floors can be poured.
Large rolls of HDPE pipe needed to be entangled and forced into more or less straight objects. Not easy with 100mtr rolls and some also heavy. Lucky we have a private road of that length and that helped.

We also needed our own electricity pole which was also delivered, planted and wired up by a Ninja with a very long bamboo ladder.
It’s a bit of a pole forest but this is the official way and it is all in sight of the neighbours, not ours.

All wired up to get a meter when the house is done more than 50%.

The next step was an earth connection. We decided to make it a 3 points system with some rather interesting way of soldering the 3 meter long pins to the wire…..

The next days I have been digging holes and pulling the tubes through the whole building